Energy




Recognizing the growing energy needs of Pakistan, and to overcome the existing deficits, CPEC has allocated a major proportion of its funds to energy generation and transmission.
The projects stated below are included in CPEC and would contribute towards the sustainable growth of industries and unhindered electric supply for domestic consumption in Pakistan.

_______________________________________________
PROJECT NAME:
2x660MW Port Qasim Coal-fired Power Plant

COMPANT NAME:
Power China Resources Ltd.

STATUS:
Under construction 60 % Done
________________________________________________

2x660MW Sahiwal Coal-Fired Power Plant

Huaneng Shandong Ruyi (Pakistan) Energy (Private) Ltd. 

Under construction 60 % Done
_______________________________________________________

4x330MW Engro Thar Coal-fired Power Plant and Surfice Mine in Block II of Thar Coal Field

China Machinery Engineering Corporation(CMEC)

Under construction 60 % Done

________________________________________________

50MW Dawood Wind Farm

Hydrochina International Engineering Co. Ltd.


Under construction/Almost Completed 90% Done

_______________________________________________


900MW Quaid-e-Azam Solar Park in Bahawalpur

Zonergy Company Ltd.


Under construction/First 300MW completed 60% done

_______________________________________________


100MW Jhimpir Wind Farm

UEP Wind Power (PVT) Ltd.

Under construction 60% Done

_______________________________________________



50MW Sachal Wind Farm


Hydrochina International Engineering Co. Ltd


Under construction 60% Done

_______________________________________________